Progress Billing for Contractors: Methods, Pay Apps and a Worked Example
How progress billing works: percent complete, milestones, schedule of values, AIA-style pay apps, stored materials and retainage, with a worked example.
Progress billing means billing a customer in stages as the work is completed, instead of one invoice at the end. The most common methods are billing by percent complete, by milestones, or against a schedule of values on an AIA-style pay application. Done well, progress billing keeps cash coming in at roughly the pace you spend it, which is the difference between a big job that funds itself and one that drains your account.
What is progress billing?
Progress billing is invoicing for the portion of the contract you’ve completed during a billing period, usually monthly. On a job that runs for months, you’re paying crews and suppliers every week. Progress billing is how you get paid along the way.
It also creates a record. Each bill shows how much of the contract is done, how much has been billed, how much is held as retainage and how much remains. That record is what owners, GCs, lenders and bonding companies look at.
Progress billing methods
Percent complete. You estimate how much of the whole job is done and bill that share of the contract, minus what you’ve already billed. It’s simple, and it works for smaller jobs. The risk is that “percent complete” becomes a guess, and guesses run optimistic.
Milestones. The contract sets payments at defined points: after excavation, after the pour, after final walkthrough. It’s clear to everyone, but if milestones are far apart, you carry a lot of cost between them. Set milestones so no gap is longer than you can afford to fund.
Schedule of values. The contract price is broken into line items, each with a value. Each period you bill the percentage complete on each line. This is the standard on commercial work and the basis of AIA-style pay applications.
How an AIA-style pay application works
Many owners and general contractors use pay application forms based on the American Institute of Architects documents, the G702 and G703, or their own version of them.
The G703 continuation sheet lists every line on the schedule of values: its value, the work completed in previous periods, work completed this period, materials stored, the total to date, the percent complete and the balance to finish.
The G702 summary page rolls those up: the original contract, approved change orders, total completed and stored to date, retainage, previous payments and the current amount due. The architect, owner or GC reviews and approves it, and some jobs require it to be notarized.
A worked example: a schedule of values pay app
Say a concrete contractor has a $250,000 contract with 10% retainage. This is pay application #2. Last month they billed $60,000. This month they finished footings, poured part of the slab and have $9,000 of rebar and mesh stored on site for the rest of it.
| Line item | Scheduled value | Previous | This period | Stored materials | Total to date | % complete | Balance to finish |
|---|---|---|---|---|---|---|---|
| Mobilization | $10,000 | $10,000 | $0 | $0 | $10,000 | 100% | $0 |
| Excavation and grading | $30,000 | $30,000 | $0 | $0 | $30,000 | 100% | $0 |
| Footings and foundation | $60,000 | $20,000 | $40,000 | $0 | $60,000 | 100% | $0 |
| Slab on grade | $90,000 | $0 | $27,000 | $9,000 | $36,000 | 40% | $54,000 |
| Flatwork and sidewalks | $45,000 | $0 | $0 | $0 | $0 | 0% | $45,000 |
| Sealing and cleanup | $15,000 | $0 | $0 | $0 | $0 | 0% | $15,000 |
| Total | $250,000 | $60,000 | $67,000 | $9,000 | $136,000 | 54.4% | $114,000 |
The summary page then works out the amount due:
| Amount | |
|---|---|
| Total completed and stored to date | $136,000 |
| Less retainage (10%) | ($13,600) |
| Total earned less retainage | $122,400 |
| Less previous payments ($60,000 less 10% retainage) | ($54,000) |
| Current payment due | $68,400 |
A quick check: this period’s work plus stored materials is $67,000 + $9,000 = $76,000, and 90% of that is $68,400. The numbers agree.
Stored materials
Stored materials are materials delivered and paid for (or owed) but not yet installed. Many contracts let you bill for them, which matters when a big order of rebar, block or coating product lands weeks before it goes in.
Expect to provide supplier invoices, proof that the materials are on site or in an approved location, and proof of insurance. Once the materials are installed, they move from “stored” to “work completed” on the next pay app; you don’t bill them twice.
Retainage on each pay app
Retainage is usually taken on each pay app as a percentage of work completed and stored to date. In the example, 10% of $136,000 is $13,600 held so far. Over the whole job, that adds up to $25,000 held until closeout.
Track it in its own account and on a retainage schedule, as covered in retainage accounting for contractors, so you know exactly what’s held on each job and what it takes to get it released.
Billing cadence and cutoff dates
Most commercial pay apps run monthly on a fixed schedule. A common setup: the GC wants pencil drafts by a set day, final pay apps a few days later, and pays a set number of days after the owner pays them.
Three habits that speed up cash:
- Know every customer’s cutoff date. Missing it by a day can push payment back a full month.
- Bill through a consistent date. Bill work through the same day each month so the numbers line up with your books and your WIP schedule.
- Include approved change orders. Add them as new lines as soon as they’re signed. Waiting until the end turns them into a negotiation (see change orders and profit).
Put your billing dates and expected payment dates into your cash-flow forecast. The construction cash flow guide explains how billing timing drives the rest of the forecast.
Common mistakes
Billing ahead of the work. Front-loading the schedule of values or overstating percent complete brings cash in early, but it creates overbillings. Your books show income you haven’t earned, and a slow finish can catch up with you.
Billing behind the work. Being conservative or late creates underbillings. You’re funding the customer’s job with your money.
Percent complete by feel. Use quantities, hours or cost-to-date against budget to back up the percentage.
Forgetting supporting documents. Missing lien waivers, certified payroll or insurance certificates are among the most common reasons a pay app gets held.
Where this breaks down
Progress billing tracks the work only as well as your job costing tracks costs. If you don’t know your cost to date on a job, you can’t tell whether your billing is ahead or behind. That comparison is what a WIP report does, and the guide to WIP reports and over/under billing walks through it.
Contract terms also vary. Some customers require their own forms, some don’t allow stored materials, and some pay on milestones only. The contract always wins over the general approach here.
Frequently asked questions
What are the AIA G702 and G703 forms?
They are standard pay application forms published by the American Institute of Architects. The G702 is the summary page with the amount due, and the G703 is the continuation sheet listing each line of the schedule of values. Many owners and GCs use them or a form based on them.
Can I bill for materials that aren't installed yet?
Often, if the contract allows it. Most contracts that allow stored materials require proof, such as invoices, photos, insurance and sometimes a bill of sale, and may require that they be stored on site or in a bonded location.
How do I bill for change orders on a pay app?
Approved change orders are usually added as new lines on the schedule of values, or in a separate change order section, and billed as they're completed. Unapproved changes generally can't be billed until they're signed.
What's the difference between progress billing and a deposit?
A deposit is paid before work starts, usually to cover materials or hold a spot on the schedule. Progress billing is payment for work already done. Some states limit deposits on residential contracts, so check the rules where you work.
Keep reading
- ArticleRetainage Accounting for Contractors: How to Record and Track ItRetainage is earned money the customer holds until the job is done. How to record retainage receivable and payable, track it, and get it released.
- GuideConstruction Cash Flow Management: A Guide for ContractorsWhy profitable contractors run out of cash, and how to fix it: billing, collections, payables, a 13-week forecast and smart use of a line of credit.
- GuideWIP Reports and Over/Under Billing: A Contractor's GuideA WIP report compares what you've earned on each job to what you've billed. Here's how to build one, read over/under billing and spot profit fade early.
- ServiceCash-flow forecastingA 13-week forecast so you see payroll problems before they hit.
- ArticleChange Orders and Profit: How Unbilled Changes Eat Your MarginUnpriced and unbilled change orders are one of the fastest ways to lose a job's profit. How to write, price, track and bill them, with a worked example.
- IndustryConstruction Accounting for General ContractorsSub buyout, general conditions, pay apps, retainage both ways and lien waivers, tracked so a few points of fade don’t wipe out your fee.