Retainage is earned money the customer holds until the job is done. How to record retainage receivable and payable, track it, and get it released.

Retainage (also called retention) is a portion of each progress payment that the customer holds back until the job is finished. It is often 5–10% of each bill, set by the contract. In your books, retainage you are owed is an asset called retainage receivable, and retainage you hold from your subcontractors is a liability called retainage payable. Tracking both by job is how you avoid finishing a profitable job with most of the profit still sitting in someone else’s account.

What is retainage?

Retainage is money you have earned but won’t receive until the job, or a defined stage of it, is complete. The owner or general contractor holds it as security that you’ll finish the punch list and deliver the closeout paperwork.

The percentage and the release terms come from the contract. Some contracts hold the same percentage for the whole job. Others drop it, for example from 10% to 5%, once the job reaches a set point. Some public and private work is governed by state laws that cap retainage or set deadlines for paying it. Read the retainage clause before you sign, not when you’re waiting on the check.

Retainage receivable vs. retainage payable

Retainage receivable is what customers are holding from you. It is an asset on your balance sheet, like regular receivables, but it isn’t collectible until the release conditions are met.

Retainage payable is what you are holding from your subs. It is a liability. You owe it, just not yet.

Both need their own accounts in your chart of accounts. If retainage receivable is mixed in with regular receivables, your receivables aging is wrong: amounts that aren’t due yet look 120 days late, and amounts that really are late get lost in the noise.

How to record retainage

Retainage is recorded when you bill, not when you’re paid. Here is an example with round numbers.

Say you bill $100,000 for work completed this month, and the contract holds 10%.

AccountDebitCredit
Accounts receivable$90,000
Retainage receivable$10,000
Contract revenue$100,000

You earned $100,000. You expect $90,000 now and $10,000 at the end.

Now say your concrete sub bills you $40,000, and your subcontract holds 10%.

AccountDebitCredit
Job cost: subcontractors$40,000
Accounts payable$36,000
Retainage payable$4,000

The full $40,000 is a job cost now. You pay $36,000 on normal terms and owe $4,000 at the end.

In QuickBooks and most construction accounting setups, this is done with retainage items or separate line items on the invoice and bill so the split happens automatically. However it’s set up, the result should be the same: retainage on its own lines, tied to the job.

How to track retainage by job

A retainage schedule is a simple list, updated each month:

  • Job name and contract amount
  • Retainage percentage, and any reduction terms
  • Retainage billed to date
  • Retainage you are holding from each sub on that job
  • Expected release date and what’s needed to get it

Reconcile the totals to the retainage receivable and payable balances on your balance sheet every month. If they don’t match, something was posted to the wrong account. This is part of keeping construction-specific bookkeeping, and it’s one of the first things a bonding company or lender will ask about.

How retainage affects cash flow

Retainage feels small on any one bill. Over a whole job, it adds up to a big share of the profit.

Here’s a worked example. Say you have a $500,000 contract with 10% retainage. You expect a 12% gross margin, or $60,000 of gross profit. Of the job’s $440,000 in costs, $200,000 is subcontracted work, and you hold 10% from the subs too.

Amount
Retainage held from you (10% × $500,000)$50,000
Retainage you hold from subs (10% × $200,000)$20,000
Net retainage tied up$30,000
Expected gross profit$60,000

You’ve paid your crew, your suppliers and 90% of your subs, and $50,000 of your money is waiting on closeout. Even after the $20,000 you are holding from subs, $30,000 is out, which is half of the job’s profit. If the owner holds the retainage for months after you finish, you are financing that part of their project.

Now put three or four of these jobs in progress at once. That’s why retainage belongs in your cash-flow forecast with a realistic release date, not the date you hope for. The construction cash flow guide covers how to build that forecast.

Retainage also shows up in your progress billing. Each pay application shows retainage held to date, so the two have to agree.

How to get retainage released

Retainage release is mostly a paperwork exercise, and slow paperwork is the most common reason it’s late.

Finish the punch list fast. Release usually requires substantial or final completion. A punch list that drags for weeks keeps the money held.

Know the closeout requirements on day one. As-builts, warranties, operation and maintenance manuals, test reports, inspection sign-offs. Collect them as the job goes, not after.

Have lien waivers ready. Owners and GCs typically want final lien waivers from you and often from your subs and suppliers before releasing final payment. If one supplier’s waiver is missing, everyone waits.

Bill it. Many contracts require a formal request or a final pay application for retainage. If you don’t send it, the clock may not start.

Follow up on a schedule. Put each release date on a calendar and call when it passes.

Where this breaks down

State law changes the picture. Some states limit retainage percentages, set deadlines to release it, require it to be held in a separate account, or require prompt payment to subs once the contractor is paid. Rules can differ for public and private work. Check the rules in the states where you work, and have an attorney look at contracts that seem unusual.

Accounting for retainage is also different from taxing it. Your books may show the revenue when billed; how and when retainage is taxed depends on your accounting method. That’s a question for your CPA.

Frequently asked questions

Is retainage income when I bill it or when I receive it?

On most accrual-based books, the revenue is recognized when the work is billed, and the held amount sits in retainage receivable until it is paid. How it is treated for income tax can depend on your accounting method, so confirm that with your CPA.

Can I hold retainage from my subcontractors?

Usually, if your subcontract says so. Many contractors pass the same retainage terms down to subs that the owner holds from them. Some states limit how much can be held and how quickly it must be paid once you are paid.

What happens to retainage if the job goes over schedule?

It stays held until the contract's conditions for release are met, which usually means substantial or final completion. A late job delays your retainage too, so schedule slips have a cash cost on top of the labor cost.

Does retainage show up on a WIP report?

Billings on a WIP report are usually gross billings, including retainage. Retainage receivable shows separately on the balance sheet. Your bonding company will look at both.