Change Orders and Profit: How Unbilled Changes Eat Your Margin

Unpriced and unbilled change orders are one of the fastest ways to lose a job's profit. How to write, price, track and bill them, with a worked example.

Change orders lose money in a simple way: the work gets done, the cost lands on the job, and the extra revenue never does. A few “while you’re here” requests on a job can take its margin from healthy to thin without anyone deciding to give the work away. The fix is a written change order process: describe it, price it with overhead and profit, get approval, track it in job costing and bill it on the next draw.

How unbilled change orders erode margin

Every change costs you labor, materials and time. If it isn’t priced and billed, that cost comes out of the profit on the original contract.

It rarely happens all at once. The customer asks the foreman to move a control joint, add a step, extend a pad two feet. The crew does it because saying no on site feels like bad service. Nobody writes it down. At the end of the job, the hours are on the timecards and the extra yards are on the concrete ticket, but the invoice still matches the original bid.

This is one of the ways a job that keeps the crew busy can still be your least profitable. The estimate was right. The scope wasn’t.

What a written change order process looks like

A change order process doesn’t need to be complicated. It needs to happen every time.

  1. Stop and write it down. Before the work starts, the foreman or PM records what changed, who asked and why. A text with photos is better than nothing.
  2. Price it. The office or the estimator prices the change using the same costs used in the original bid.
  3. Get approval in writing. A signature, an email reply or an approval in your estimating and project-management software. Match what your contract requires.
  4. Add it to the job. The change goes into job costing as its own line, with its own budget.
  5. Bill it. The approved change goes on the next invoice or pay application.

Give your field leads a clear rule: no extra work without a written note to the office first. It protects them as much as it protects the company.

How to price a change order

Price a change order the same way you price a job, then think about what it does to the schedule.

Direct cost. Labor at its true burdened rate (see how to calculate labor burden), materials, equipment, subs and any added permits or disposal.

Schedule impact. This is the part that gets left out. A change can mean an extra trip, a crew sitting idle while a decision gets made, a longer equipment rental or a second mobilization. Those are real costs of the change, and they are often larger than the work itself.

Overhead and profit. Add your overhead and profit the way you would on any job. If your overhead percentage is 15% and you target 10% profit, you need a 25% margin on the change, not a 25% markup. The markup vs. margin calculator converts one to the other.

Some contracts cap the overhead and profit allowed on changes, or require a specific format with backup. Read the change clause before you price.

How to track change orders in job costing

Each change order should be a separate line in your job budget, with its own estimated cost and its own revenue. Don’t fold it into the original numbers.

Keeping them separate answers two questions you’ll want answered at the end of the job: how did we do on the base bid, and how did we do on the changes? If you mix them, a loss on the base bid can hide behind a profitable change, or the other way around.

Code the labor and materials for a change to that change. If your crew uses cost codes on their timecards, give the change its own code. This is where job costing for contractors pays off, because the hours and materials are already sorted by the time the job closes.

Why bill change orders promptly

An approved change order is revenue you have earned. Holding it until the end of the job has three costs.

Cash. You’ve already paid for the labor and materials. Waiting to bill means waiting longer to be paid.

Memory. Customers who approved a change in April are less sure about it in September. A change billed the next month gets paid. A stack of changes billed at closeout gets negotiated.

Retainage and closeout. If changes are left to the final bill, they get tangled with punch lists, lien waivers and retainage release, and everything slows down.

Put approved changes on the next invoice or pay application, as their own lines.

A worked example

Say a contractor bids a commercial flatwork job at $80,000, with estimated costs of $60,000. That’s $20,000 of planned gross profit, a 25% margin.

During the job, the customer asks for three changes: a thicker slab section, an added sidewalk and a revised drain location. Together they cost $6,000 in labor and materials. The drain change means waiting two days for a decision and coming back, which adds $1,500 in remobilization and an extended equipment rental. The total cost of the changes is $7,500.

Priced at the same 25% margin, the changes sell for $7,500 ÷ (1 − 0.25) = $10,000.

Changes not billedChanges priced and billed
Revenue$80,000$90,000
Costs$67,500$67,500
Gross profit$12,500$22,500
Gross margin15.6%25.0%

The costs are the same in both columns. The only difference is whether the paperwork happened. Without it, the job lost $7,500 of its planned profit, and if overhead runs 15% of revenue, a 15.6% margin leaves almost nothing.

Notice too what happens if you price only the $6,000 of visible work and skip the schedule impact: at 25% margin that’s $8,000, and the $1,500 of remobilization still comes out of your profit.

Common mistakes

Pricing changes at cost. Doing extra work at cost “to keep the customer happy” means doing it for free once overhead is counted.

Letting the field approve and price on the spot. Foremen should capture the change; the office should price it from real numbers.

Not tracking the cost of disputed changes. If a change is in dispute, track its actual cost carefully anyway. You can’t negotiate a number you never recorded.

Billing at the end. Covered above, and worth saying twice.

Where this breaks down

Some work is genuinely hard to price up front, like unknown conditions under a slab or hidden damage in a remodel. For that, agree in writing on how it will be priced, such as time and materials at set rates, before the work starts. The process still holds: write it down, track the actual cost, bill it promptly.

Frequently asked questions

Should I charge overhead and profit on a change order?

Yes. A change uses the same office, insurance, trucks and management time as the original work, and often more of it per dollar. Your contract may set the allowed overhead and profit percentage on changes, so check it before you price.

What if the customer won't sign before I start?

At minimum, send a written description of the change and a statement that it is extra work, by email or text, before you do it. Some contracts require signed approval before you are entitled to payment, so a verbal yes may not hold up. Know what your contract says.

How do I handle change orders on a fixed-price job?

The original scope stays fixed-price, and each change gets its own price on top. Keep the original budget unchanged in your job costing and add the change as a separate line, so you can still see how you did on the base bid.

What's the difference between a change order and a change directive?

A change order is agreed and priced by both sides. A change directive, used in some contracts, orders the work before the price is agreed. The price gets settled later, which is why tracking the actual cost of directed work is so important.