WIP Reports and Over/Under Billing: A Contractor's Guide
A WIP report compares what you've earned on each job to what you've billed. Here's how to build one, read over/under billing and spot profit fade early.
A work-in-progress (WIP) report is a schedule of every open job that compares the revenue you’ve actually earned, based on how far along the job is, to what you’ve billed the customer. The difference is your over billing or under billing. It’s the report that tells you whether your jobs are making the profit you expected and whether your invoices are ahead of or behind the work. Bonding companies, banks and CPAs ask for it because it shows the truth about open jobs that a profit and loss can’t.
What is a WIP report?
A WIP report is a monthly snapshot of every contract that’s started but not finished. For each job it lines up the contract value, the estimated total cost, how much you’ve spent, how much you’ve billed, and how much revenue you’ve earned so far.
The reason it exists: on long jobs, billing and work don’t move together. You might bill 40% of a contract in the first month because the schedule of values was front-loaded, while only 20% of the work is done. Or you might be three months into a job with half the work in place but have only billed a third because a pay application got held up. If you count revenue as whatever you’ve invoiced, your profit swings around based on billing timing, not on how the jobs are actually going.
The WIP report fixes that by measuring revenue by progress. Most contractors measure progress with the cost-to-cost method.
Who asks for a WIP report?
Bonding companies (sureties). If you need performance and payment bonds, your surety will want a WIP schedule, often quarterly and with your year-end financial statements. They use it to judge whether you can finish the work you already have before they back more of it.
Banks and lenders. A line of credit or equipment loan often comes with reporting requirements. Lenders read the WIP to see whether your receivables and profit are real.
Your CPA. If your financial statements are prepared on a percentage-of-completion basis, the WIP schedule is where the year-end revenue adjustment comes from.
You. Even if nobody outside the company asked, the WIP report is the best single page for seeing which open jobs are on track and which are fading.
How percentage of completion works (cost-to-cost)
Percentage of completion is a way of recognizing revenue and profit as the job progresses, instead of all at once at the end. The cost-to-cost method measures progress by how much of the estimated cost you’ve incurred.
The math is three steps:
- Percent complete = cost to date ÷ estimated total cost
- Earned revenue = percent complete × contract value
- Over/under billing = billed to date − earned revenue
If the result in step 3 is positive, you’re overbilled: you’ve invoiced more than you’ve earned. If it’s negative, you’re underbilled: you’ve earned more than you’ve invoiced.
Say a job has a $100,000 contract and $80,000 of estimated cost. You’ve spent $40,000, so the job is 50% complete. Earned revenue is 50% of $100,000, or $50,000. If you’ve billed $60,000, you’re overbilled by $10,000. If you’ve billed $45,000, you’re underbilled by $5,000.
The method assumes cost is a fair measure of progress. That’s usually reasonable, with one catch: it only holds if the estimated total cost is right. If the estimate is stale, every number downstream is wrong. More on that below.
The columns of a WIP schedule
Formats vary, but most WIP schedules carry these columns:
- Contract value. The original contract plus approved change orders. Pending change orders are usually left out until they’re approved, or tracked separately.
- Estimated total cost. What you now expect the job to cost when finished: cost to date plus the project manager’s current estimate of cost to complete. Not the original bid, unless nothing has changed.
- Estimated gross profit. Contract value minus estimated total cost. This is what the job is expected to make, and it changes when the cost estimate changes. Divided by contract value, it’s your expected gross margin, which is not the same as markup; the markup vs margin calculator shows the difference.
- Cost to date. All direct costs posted to the job through the end of the month: labor with burden, materials, subs, equipment and other direct costs.
- Percent complete. Cost to date divided by estimated total cost.
- Earned revenue. Percent complete times contract value.
- Billed to date. Everything you’ve invoiced on the job, typically including retainage the customer is holding.
- Over/(under) billing. Billed to date minus earned revenue.
- Cost to complete. Estimated total cost minus cost to date: what you still expect to spend.
Many schedules also show gross profit earned to date (earned revenue minus cost to date) and the original estimated gross profit, so you can see how expectations have moved since the bid.
Worked example: a three-job WIP schedule
Say a commercial concrete contractor has three open jobs at the end of the month. These are example numbers.
| Job A | Job B | Job C | Total | |
|---|---|---|---|---|
| Contract value (incl. change orders) | $500,000 | $250,000 | $120,000 | $870,000 |
| Estimated total cost | $400,000 | $200,000 | $90,000 | $690,000 |
| Estimated gross profit | $100,000 | $50,000 | $30,000 | $180,000 |
| Cost to date | $200,000 | $150,000 | $18,000 | $368,000 |
| Percent complete | 50% | 75% | 20% | |
| Earned revenue | $250,000 | $187,500 | $24,000 | $461,500 |
| Billed to date | $300,000 | $150,000 | $30,000 | $480,000 |
| Over/(under) billing | $50,000 | ($37,500) | $6,000 | $18,500 |
| Cost to complete | $200,000 | $50,000 | $72,000 | $322,000 |
Walking through the math:
- Job A: $200,000 ÷ $400,000 = 50% complete. 50% × $500,000 = $250,000 earned. Billed $300,000, so overbilled by $50,000. Cost to complete is $400,000 − $200,000 = $200,000.
- Job B: $150,000 ÷ $200,000 = 75% complete. 75% × $250,000 = $187,500 earned. Billed $150,000, so underbilled by $37,500. Cost to complete is $50,000.
- Job C: $18,000 ÷ $90,000 = 20% complete. 20% × $120,000 = $24,000 earned. Billed $30,000, so overbilled by $6,000. Cost to complete is $72,000.
The company is overbilled $56,000 on two jobs and underbilled $37,500 on one, for a net overbilling of $18,500. Total percent complete isn’t summed; the per-job percentages are what matter.
What this schedule tells you:
- Job A is billing well ahead of the work. $50,000 of the cash you’ve collected or will collect on it hasn’t been earned. That money pays for the $200,000 of work still to do.
- Job B needs a closer look. Underbilled by $37,500 at 75% complete. Either a pay application is behind (fixable: bill it), or the job has used more cost than expected and isn’t really 75% done (a problem). The project manager’s answer to “is this job really three-quarters done?” decides which.
- Job C is early and slightly ahead on billing. Normal for a job that just started, especially if mobilization was billed up front.
What overbilling means
Overbilling means you’ve invoiced more than you’ve earned. On the balance sheet it’s a liability, usually called “billings in excess of costs and estimated earnings.” You owe the customer work for money you’ve already billed.
A modest overbilling is normal and often healthy. Front-loaded schedules of values, mobilization billing and deposits all create it, and it means the customer is financing part of the job instead of you.
The danger is treating overbilling as profit. The cash from Job A’s $50,000 overbilling feels like money in the bank, but it’s committed to finishing Job A. If it gets spent on payroll for another job, a new truck or the owner’s draw, you’ll reach the end of Job A with costs left and no billings left to cover them. That’s how contractors get caught in a cycle of needing new jobs with front-loaded billing to pay for finishing old ones. Overbilling is a cash crutch when it’s the only thing keeping the account positive. Our construction cash flow guide covers how to keep that cash in its place.
What underbilling means
Underbilling means you’ve earned more than you’ve invoiced. On the balance sheet it’s an asset, usually called “costs and estimated earnings in excess of billings.” In theory, it’s money the customer owes you for work in place.
Sometimes that’s exactly what it is: a pay application that went out late, a change order that’s approved but not yet billed, or a billing schedule that lags the work. Those are cash problems with a direct fix. Tighten your progress billing and bill what you’ve earned.
But chronic underbilling is a warning sign, and sureties and lenders know it. Under cost-to-cost, spending more makes a job look more complete. If a job is running over budget and nobody has updated the estimated total cost, the extra cost pushes percent complete up, earned revenue goes up with it, and the job shows an underbilling that will never be collected. The “asset” is really a cost overrun that hasn’t been admitted yet. When underbillings show up job after job, month after month, assume it’s this until proven otherwise.
Profit fade and profit gain
Profit fade is when a job’s expected gross profit drops over its life. Profit gain is the reverse. Both show up on the WIP when the estimated total cost changes.
Go back to Job B. Say the project manager reviews the job and admits it will take another $90,000 to finish, not $50,000. The estimated total cost rises from $200,000 to $240,000.
| Job B | Before update | After update |
|---|---|---|
| Contract value | $250,000 | $250,000 |
| Estimated total cost | $200,000 | $240,000 |
| Estimated gross profit | $50,000 | $10,000 |
| Cost to date | $150,000 | $150,000 |
| Percent complete | 75% | 62.5% |
| Earned revenue | $187,500 | $156,250 |
| Billed to date | $150,000 | $150,000 |
| Over/(under) billing | ($37,500) | ($6,250) |
| Gross profit earned to date | $37,500 | $6,250 |
Nothing about the work or the billing changed. The only change was an honest cost estimate. Expected profit on the job fell from $50,000 to $10,000, and $31,250 of profit that had looked earned ($37,500 − $6,250) comes off the books this month. The underbilling mostly disappears, because most of it was never real.
That’s why a profit fade on a WIP report hurts in the month you recognize it. It’s also why waiting doesn’t help: the overrun happened whether or not you admit it, and the longer the estimate stays stale, the bigger the eventual adjustment and the more profit you reported that wasn’t there. A job that shows steady fade from month to month is one where the estimate isn’t being updated honestly, or where the job keeps finding new problems. Either way, it needs attention now. Unbilled extra work is a common cause, so check whether there are change orders you should be writing.
How often should you run a WIP report?
Run it every month, after the books are closed. Monthly is often enough to catch fade while you can still act on it, and it keeps the schedule current for the quarterly or annual versions bonding companies and banks ask for.
A WIP that only gets built once a year for the surety is a scramble every time, and by then problems are months old. Monthly WIP requires the same groundwork as good job costing: every cost coded to the right job by month end, payroll posted with burden, change orders entered, and billings current. If that groundwork isn’t there, start with job costing.
Why project managers must update estimates to complete
The most important number on a WIP report is the one accounting can’t produce on its own: the estimated cost to complete each job. Accounting knows what’s been spent. Only the people running the job know what’s left.
Every month, the project manager or the person running each job should review it and answer: given what’s done and what’s left, what will it cost to finish? That review should consider:
- Labor hours remaining against the crew’s actual production so far, not the bid’s assumed rate.
- Materials and subcontracts already committed but not yet billed.
- Known problems: rework, delays, design changes, a sub that’s struggling.
- Approved and pending change orders, and the cost tied to each.
If the estimate to complete never changes from the original bid, the WIP report is just the bid with percentages attached. Cost-to-cost math needs a live estimate to mean anything. Our job costing service sets up the budget structure that makes this monthly review straightforward.
Common WIP report mistakes
Using the original bid as the estimated total cost forever. The single most common mistake, and the one that hides fade until the job closes.
Leaving out approved change orders, or including unapproved ones. Approved changes belong in contract value and in estimated cost. Pending ones can be tracked separately, but counting revenue you haven’t secured overstates profit.
Costs not posted by month end. If a big material invoice is sitting in someone’s truck, cost to date is understated, percent complete is understated, and the job looks overbilled when it isn’t.
Mishandling retainage. Retainage the customer holds is still billed revenue; it’s a receivable, not missing billing. Leaving it out of billed to date makes jobs look underbilled. See our article on retainage accounting.
Treating overbilling as cash you can spend. It’s committed to the work.
Explaining away underbillings. “We’ll catch it on the next pay app” is sometimes true. Check the cost estimate before you believe it.
Including uninstalled materials without thought. A large material delivery stored on site pushes cost to date up without much progress. Many contractors exclude stored materials from cost-to-cost progress or adjust for them; decide on a consistent approach with your CPA.
Assuming the WIP sets your tax method. How you recognize revenue on your financial statements and how you report it for taxes can differ. Confirm both your revenue-recognition approach and your tax accounting method with your CPA.
Frequently asked questions
What is a WIP report in construction?
A WIP (work-in-progress) report is a schedule of every open job showing the contract value, estimated cost, cost to date, percent complete, earned revenue, amount billed and the resulting over or under billing. It tells you whether each job is making the profit you expected and whether your billing is ahead of or behind the work. Bonding companies and banks commonly ask for one.
Is overbilling bad?
Not by itself. Billing slightly ahead of the work is common and helps cash flow, especially with front-loaded schedules of values. It becomes a problem when the cash from overbilling gets spent on other things, because you still owe the work and will have to pay for it later without the matching income.
Why does underbilling worry bonding companies?
Underbilling can mean you simply haven't invoiced work you've done, which is a cash problem you can fix. But it often means costs are running ahead of the estimate, so the cost-to-cost math shows more progress than the job really has. Sureties and lenders see consistent underbilling as a possible sign of profit fade that hasn't been admitted yet.
Do small contractors need a WIP report?
If you have jobs that span more than a month or two, progress bill, or want bonding or a line of credit, yes. Even if nobody outside the company asks for it, a WIP report is the clearest monthly view of whether your open jobs are on track. Smaller contractors with short jobs can often get by with good job costing alone.
Does my WIP report determine how I pay taxes?
Not on its own. Revenue recognition for your financial statements and the accounting method you use for taxes can differ, and the rules for which contractors can use which tax method depend on factors like company size and contract length. Confirm both with your CPA; the WIP schedule provides the job data either way.
Keep reading
- GuideJob Costing for Contractors: The Complete GuideJob costing tracks every dollar of labor, materials, subs and equipment against the job that caused it. How to set it up, run it and use it to bid better.
- ServiceJob costing & systemsProfit by job while the job is still running.
- ArticleProgress Billing for Contractors: Methods, Pay Apps and a Worked ExampleHow progress billing works: percent complete, milestones, schedule of values, AIA-style pay apps, stored materials and retainage, with a worked example.
- ArticleRetainage Accounting for Contractors: How to Record and Track ItRetainage is earned money the customer holds until the job is done. How to record retainage receivable and payable, track it, and get it released.
- GuideConstruction Cash Flow Management: A Guide for ContractorsWhy profitable contractors run out of cash, and how to fix it: billing, collections, payables, a 13-week forecast and smart use of a line of credit.
- ArticleChange Orders and Profit: How Unbilled Changes Eat Your MarginUnpriced and unbilled change orders are one of the fastest ways to lose a job's profit. How to write, price, track and bill them, with a worked example.
- IndustryConstruction Accounting for General ContractorsSub buyout, general conditions, pay apps, retainage both ways and lien waivers, tracked so a few points of fade don’t wipe out your fee.
- ServiceFractional CFOForecasts, budgets, WIP and strategy meetings for $3M+ contractors.