How to Calculate Labor Burden for Construction Crews

Labor burden is what an hour of labor really costs you beyond the wage. Here's how to calculate it, step by step, with a worked example.

Labor burden is the cost of an employee’s hour beyond the wage you pay them: employer payroll taxes, workers’ comp, benefits, paid time off and the paid hours nobody can bill. To calculate it, add those costs to the wage, then divide by the share of paid hours that actually land on a job. A $28-an-hour crew member does not cost you $28 an hour, and bids built on the wage alone lose money quietly.

What is labor burden?

Labor burden is every cost that comes with an hour of labor, on top of the hourly wage. It is usually shown either as dollars per hour or as a percentage of the wage.

It matters because you sell hours. If the hour you sell costs more than you think, every bid is underpriced by the same hidden amount, and the busier you get the more it costs you.

What goes into labor burden

Burden has five main pieces. Some are set by law, some by your insurance carrier, and some by your own choices.

Employer payroll taxes. You pay the employer half of Social Security and Medicare, which is 7.65% of wages (the Social Security part stops once an employee passes an annual wage cap). On top of that you pay federal unemployment tax and state unemployment tax. Unemployment taxes usually apply only to the first portion of each employee’s wages, and state rates vary by state and by your claims history. Your payroll reports show what you actually paid.

Workers’ comp. Premiums are set by class code and by state, usually as a rate per $100 of payroll. Concrete, roofing and framing class codes often run far higher than clerical codes. Use your policy, not a guess, and remember the audit at year end can change the number.

Benefits. Health insurance, retirement contributions, a truck allowance, phone stipends, tools. Turn each into a cost per paid hour.

Paid time off. Holidays, vacation and sick pay are hours you pay for with no work done. Count PTO either as a benefit per hour or as unbillable time, but not both.

Unbillable time. Drive time, shop time, loading the truck, safety meetings, weather days you pay for, warranty callbacks. Your crew is on the clock, but no customer is paying for it. This is the piece most contractors leave out, and it often moves the number more than anything else.

How to calculate labor burden, step by step

SarokaFi uses this formula, the same one behind our labor burden calculator:

True labor cost per hour = (wage × (1 + payroll taxes % + workers’ comp %) + benefits per hour) ÷ (1 − unbillable %)

Here is a worked example. Say a concrete finisher earns $28.00 an hour. The numbers below are an example, not anyone’s actual rates.

  • Employer payroll taxes: 10% of wages (7.65% FICA plus federal and state unemployment, averaged across the year)
  • Workers’ comp: 8% of wages
  • Benefits: $2.00 per paid hour
  • Unbillable time: 15% of paid hours

Step 1. Add percentage-based costs to the wage. $28.00 × (1 + 0.10 + 0.08) = $28.00 × 1.18 = $33.04.

Step 2. Add benefits per hour. $33.04 + $2.00 = $35.04. That is the cost of one paid hour.

Step 3. Spread it over billable hours. Only 85% of paid hours land on a job, so $35.04 ÷ 0.85 = $41.22 per billable hour.

PiecePer billable hour
Wage$28.00
Payroll taxes (10%)$2.80
Workers’ comp (8%)$2.24
Benefits$2.00
Paid hours you can’t bill (15%)$6.18
True labor cost$41.22

You can check step 3 with annual hours. At 2,080 paid hours a year, the finisher costs $35.04 × 2,080 = $72,883.20. With 15% unbillable, only 1,768 of those hours are billable. $72,883.20 ÷ 1,768 = $41.22. Same answer.

How to turn it into a burden percentage

Burden percentage is the extra cost divided by the wage. In the example: ($41.22 − $28.00) ÷ $28.00 = $13.22 ÷ $28.00 = about 47%.

Some people quote burden without the unbillable step. On that basis it would be ($35.04 − $28.00) ÷ $28.00 = about 25%. Both are “labor burden”, which is why comparing percentages between companies is risky. For pricing, the number that matters is the cost per billable hour, because billable hours are the only ones a customer pays for.

How to use the number in your bids

Once you know the true cost of a billable hour, use it as the labor cost in every estimate. Then add overhead and profit on top. Labor burden is still a direct job cost. Your office rent, the estimator’s salary and your own pay are overhead, and they belong in your overhead percentage, not here.

From there the guide to pricing construction jobs walks through building a price that covers labor, materials, overhead and profit. If you mix up markup and margin when you add those on, the markup vs. margin calculator shows the difference in dollars.

The same rate should flow into your job cost reports. If your job costing shows wages only, the estimate and the actuals are measuring two different things, and every job looks better than it is.

Common mistakes

Using the wage as the cost. The most common one. It makes every bid look competitive, and the gap shows up only at year end.

Leaving out unbillable time. In the example it added $6.18 an hour, more than taxes or comp. A crew that drives an hour each way to a rural pour has a much higher unbillable share than a crew working in town.

Using last year’s comp rate. Rates change at renewal, and the year-end audit can reclassify payroll. Update the number when the policy changes.

Applying one rate to everyone. A foreman at $38 and a laborer at $20 carry different burden in dollars. If your crews vary, calculate by role.

Counting PTO twice. If holiday and vacation pay are already in your unbillable hours, don’t add them again as a benefit.

Forgetting that unemployment taxes front-load. Because they often apply only to the first part of each employee’s wages, they hit hardest early in the year. An annual average is fine for pricing, but expect payroll to cost more in the first months.

Where this breaks down

The formula gives you an average. Real weeks vary. A rainy spring raises unbillable time; a long job close to the shop lowers it. If your work is seasonal, calculate unbillable time over a full year, not your best month.

It also assumes the hours you track are real. If timecards are filled in from memory on Friday, the burden math is only as good as the guess. Accurate time by job is the foundation; the formula just turns it into a price.

Frequently asked questions

What is a typical labor burden percentage for construction?

There is no single right number. It depends on your state's unemployment rates, your workers' comp class codes, what benefits you offer and how much paid time your crew spends off the job. Run your own numbers instead of borrowing someone else's percentage.

Is overtime part of labor burden?

Overtime is a wage cost, not burden, but it raises your payroll taxes because those are a percentage of wages. If a job will run overtime, price the higher wage and let the burden math follow it.

Should I calculate burden for each employee or for the whole crew?

Both are useful. A crew-average rate is fine for most bids. If your wages or comp class codes vary a lot from person to person, calculate a rate per employee or per class so a foreman-heavy crew isn't priced like a laborer-heavy one.

Do I include labor burden in job costing?

Yes. If your job cost reports only show gross wages, every job looks more profitable than it is. Apply burden to job labor so the job report matches what the hours really cost you.